PROJECT DESCRIPTION

Project Goals and Schedule (as of December 2025)

The “H2 Backbone WAG + Penta-West” project is based on long-term planning with several project phases, which are structured as follows.

Feasibility
Current Phase
Planned Front End Engineering Design „FEED“
2024
Planned Final Investment Decision “FID”
2029
Planned start of construction
2029
Planned commissioning
Early 2030's